Title: Authorization to negotiate and enter into a contract with Zoon Engineering in an amount not to exceed $550,000 for Construction Management Services for the Palo Alto Horizontal Levee project
Attachments: 1. 06c 1 Summary Sheet Zoon Engineering v1.pdf, 2. 06c 2 Summary Approval Zoon Engineering v1.pdf
Date Ver.Action ByActionResultAction DetailsMeeting DetailsAudio/Video
No records to display.

Subject:

Title

Authorization to negotiate and enter into a contract with Zoon Engineering in an amount not to exceed $550,000 for Construction Management Services for the Palo Alto Horizontal Levee project

Body

 

Presenter:

Presenter

Caitlin Sweeney

 

Body

Recommended Action:

Action

ABAG Executive Board Approval

 

Body

Attachments: