File #: 20-1213    Version: 1 Name:
Type: Contract Status: Committee Approval
File created: 8/4/2020 In control: Operations Committee
On agenda: 9/11/2020 Final action:
Title: Contracts to Deliver Bay Bridge Forward (2020) i. Contract - I-580 Westbound High Occupancy Vehicle Lane Extension: Kimley-Horn & Associates, Inc. ($1,485,000); ii. Contract - I-80 Westbound High Occupancy Vehicle Lane Extension: Verano Technical Services, Inc. ($640,000); iii. Contract - I-80/Powell Street Interchange Transit Access Improvements: T.Y. Lin International ($1,250,000); iv. Contract - I-80 Design Alternative Assessment: HDR Engineering, Inc. ($1,246,000); and v. Contract - Bay Bridge Forward (2020) Program/Project Manager: Gray-Bowen-Scott ($349,000) Contracts to deliver Bay Bridge Forward (2020) operational projects.
Attachments: 1. 5a_Bay Bridge Forward_Contracts.pdf

Subject:

Title

Contracts to Deliver Bay Bridge Forward (2020)

i. Contract - I-580 Westbound High Occupancy Vehicle Lane Extension: Kimley-Horn & Associates, Inc. ($1,485,000);

ii. Contract - I-80 Westbound High Occupancy Vehicle Lane Extension: Verano Technical Services, Inc. ($640,000);

iii. Contract - I-80/Powell Street Interchange Transit Access Improvements: T.Y. Lin International ($1,250,000);

iv. Contract - I-80 Design Alternative Assessment: HDR Engineering, Inc. ($1,246,000); and

v. Contract - Bay Bridge Forward (2020) Program/Project Manager: Gray-Bowen-Scott ($349,000)

 

Contracts to deliver Bay Bridge Forward (2020) operational projects.

 

Body

 

Presenter:

Presenter

Kevin Chen

 

Body

Recommended Action:

Action

Committee Approval

 

Body

Attachments: