Title: Contract Contingency Increase - I-580 Richmond-San Rafael (RSR) Bridge Access Improvement Project -Construction Package "A" Eastbound Third Lane and Point Molate Bicycle/Pedestrian Path: O.C. Jones and Sons, Inc. ($1,500,000) A request to increase the contract contingency for the O.C. Jones and Sons, Inc. (O. C. Jones) contract in an amount not to exceed $1,500,000 to complete the remaining construction and close out the I-580 Richmond-San Rafael Bridge Access Improvement Project (the Project) - Construction Package A.
Attachments: 1. 3b_ContractContingencyIncrease_RSRbridge_OCJones_x.pdf

Subject:

Title

Contract Contingency Increase - I-580 Richmond-San Rafael (RSR) Bridge Access Improvement Project -Construction Package “A” Eastbound Third Lane and Point Molate Bicycle/Pedestrian Path: O.C. Jones and Sons, Inc. ($1,500,000)

 

A request to increase the contract contingency for the O.C. Jones and Sons, Inc. (O. C. Jones) contract in an amount not to exceed $1,500,000 to complete the remaining construction and close out the I-580 Richmond-San Rafael Bridge Access Improvement Project (the Project) - Construction Package A.

.Body

 

Presenter:

Presenter

Chris Lillie

 

Body

Recommended Action:

Action